Eastside Gibraltar Development Timeline

1st December 2025
Home > News > Eastside Gibraltar Development Timeline

What’s Coming Next?

Eastside Gibraltar Development Timeline – What’s Coming Next?

Eastside Gibraltar is entering a new phase of transformation, with several key developments at different stages of progress. Rather than focus on exact completion dates, this article provides a simple, high-level look at where each project currently stands and what is likely to happen next.

For a broader overview of the area, including lifestyle, infrastructure and existing buildings such as The Hub, E1 and Forbes, you can read our main Eastside Gibraltar Real Estate Guide.

At a glance — Eastside development timeline

  • Eastside is in an active multi-phase regeneration, with several new schemes moving through demolition, groundworks, superstructure and finishing stages.
  • This timeline focuses on Citihome, One Bayside, Elysium Bayside, Keystone Residence and Monument Place & Monument Plaza and where each stands right now.
  • Citihome is in its final construction stages, while One Bayside is close to completing its main structure.
  • Elysium Bayside and Keystone Residence are earlier in the cycle, progressing from site clearance and demolition into foundations and vertical build.
  • Monument Place & Monument Plaza have full planning permission and sit in the pre-construction phase, with groundwork and enabling works expected ahead of vertical construction.
  • The sequence shown here is indicative only; dates and phasing can change as planning, contractor and market conditions evolve.
  • Century 21 Gibraltar tracks these projects closely and helps buyers and investors match their plans to the right development and stage of construction.

Eastside Development Timeline at a Glance (Indicative)

The following sequence is indicative only and based on current visible progress and public information. Exact dates and phasing may change.

  • Citihome – late-stage construction, exterior largely complete, internal and final works ongoing.
  • One Bayside – concrete frame nearly finished, moving towards facade and internal fit-out.
  • Elysium Bayside – ground cleared, site prepared for construction to begin.
  • Keystone Residence – demolition and site preparation underway.
  • Monument Place & Monument Plaza – full planning granted, pre-construction phase, groundwork and enabling works expected ahead of vertical construction.

Citihome – Approaching Completion

Current Status

Citihome is one of the Eastside projects closest to completion. Scaffolding has largely come down and the crane is still in place, indicating that the main structure is finished and the development is in its final construction stages. At this point, a significant amount of work typically focuses on interior finishes, common areas and services.

What Happens Next

  • Completion of internal fit-out and building services.
  • Final inspections, snagging and certification.
  • Handover to owners and tenants once the building is signed off.

As Citihome moves towards completion, it will add another modern residential option to Eastside and help define the look and feel of the northern entrance into Gibraltar.

One Bayside – Structure Nearly Finished

Current Status

One Bayside is located at the junction of Bayside Road and Winston Churchill Avenue, at a key gateway into Gibraltar. The concrete frame is nearly finished, which means the main superstructure is in place and the development is progressing well above ground level.

What Happens Next

  • Completion of the last elements of the frame and roof structure.
  • Installation of the outer envelope, facade and windows.
  • Internal layout, fit-out and finishing of apartments and shared amenities such as the pool, gym and stores.

Once complete, One Bayside will further reinforce the trend of turning former industrial areas into modern residential districts and will form part of the wider Eastside and Bayside regeneration story.

Elysium Bayside – Ground Cleared, Construction to Follow

Current Status

Elysium Bayside has already reached a key early milestone: the ground has been cleared and the site has been prepared for construction. This marks the transition from planning and design into the pre-construction phase, where foundations and the main structure can start once all technical and logistical conditions are in place.

What Happens Next

  • Foundation and substructure works once construction formally begins.
  • Vertical build-up of the main residential structure.
  • Progressive delivery of floors, facades and internal spaces over time.

Because it is still at the start of its build journey, Elysium Bayside is an example of how Eastside continues to attract new projects and long-term investment interest.

Keystone Residence – Demolition and Site Preparation

Current Status

Keystone is at an earlier point in the development cycle. Demolition work has started, which means older structures are being removed to make way for the new scheme. This phase is essential to prepare the footprint, confirm ground conditions and set the stage for future construction.

What Happens Next

  • Completion of demolition and clearance of the existing buildings.
  • Site investigations and any required ground remediation or reinforcement.
  • Foundation works and the start of the main structure once preparations are finished.

As Keystone progresses from demolition into construction, it will add to the growing cluster of new-build developments in Eastside and further change the skyline of the area.

Monument Place & Monument Plaza – Planning Approved, Pre-Construction Stage

Current Status

Monument Place and Monument Plaza have full planning permission and represent one of the most ambitious mixed-use projects in Eastside. The proposal includes a new Gibraltar International College, extensive tech office space and a residential component targeted at the mid-range market, addressing the gap between affordable and high-end developments.

At the time of writing, the crane is not yet up, which suggests the project is in a pre-construction stage, focusing on detailed technical planning, procurement and enabling works.

What Happens Next

  • Groundwork, early civil engineering and site preparation.
  • Start of structural works once all pre-construction steps are completed.
  • Progressive delivery of the educational, office and residential elements.

When built, Monument Place and Monument Plaza will combine education, technology and housing in a single hub, supporting both Eastside’s economic ecosystem and Gibraltar’s long-term skills base.

What This Means for Buyers and Investors

Taken together, Citihome, One Bayside, Elysium Bayside, Keystone and Monument Place & Monument Plaza show how much of Gibraltar’s new housing and regeneration is now focused on the eastern side of the Rock. Although exact timings can shift, the overall direction is clear: Eastside is evolving into a mature residential and mixed-use district with a wide range of property types.

  • Short- and medium-term delivery of new homes as Citihome and One Bayside move towards completion.
  • Medium-term opportunities as Elysium Bayside and Keystone progress through their build cycles.
  • Longer-term vision at Monument Place and Monument Plaza, combining education, tech and residential uses.

For buyers and investors, this creates a layered set of options, from near-term completion stock to longer-term off-plan strategies. It also reinforces Eastside’s role as one of Gibraltar’s most important growth areas.

How Century 21 Gibraltar Can Help

Century 21 Gibraltar follows the progress of Eastside developments closely and can advise on availability, pricing and likely timelines based on up-to-date local knowledge. Whether you are interested in near-complete projects such as Citihome and One Bayside or earlier-phase schemes like Elysium Bayside and Keystone, our team can help you match your goals to the right development and stage of construction.

To understand Eastside in its wider context, including established buildings, future infrastructure and lifestyle considerations, we recommend starting with our main Eastside Gibraltar Real Estate Guide. From there, our advisors can provide tailored guidance on individual projects and investment opportunities.

Featured Gibraltar Properties

Explore our latest rental and sales listings across Gibraltar:

Properties for Sale Properties to Rent

Frequently Asked Questions About the Eastside Gibraltar Development Timeline

Q1: What stage is the Eastside Gibraltar Project currently at?
The project is progressing in phases, starting with coastal protection works and marina infrastructure, followed by residential and commercial construction. This timeline provides a high-level overview based on current visible progress and public information, and will evolve as new milestones are reached.

Q2: Can the Eastside Gibraltar development timeline change?
Yes. Large-scale coastal and urban projects are influenced by planning approvals, contractor programmes, market conditions and environmental requirements. Dates and phases are indicative and may shift as the project evolves, so it is important to treat the timeline as a guide rather than a fixed schedule.

Q3: How does the development timeline affect buyers and investors?
Understanding the order of phases helps buyers and investors see when different parts of Eastside are likely to complete, when amenities such as the marina, college and new residential buildings may be delivered, and how construction activity could affect short and medium-term rental or resale strategies.

Q4: Will there be disruption for nearby residents during construction?
As with any major development, there will be periods of construction noise, traffic and on-site activity. The project is phased and subject to planning conditions that typically include mitigation measures, but some disruption is inevitable as Eastside continues to grow.

Q5: Where can I get personalised advice about timing my purchase or investment?
Century 21 Gibraltar closely follows the progress of Eastside and other key projects on the Rock. Our team can help you interpret the development timeline in the context of your goals, whether you are buying a home, planning a relocation or targeting rental yields. For broader context, you can also read our main Eastside Gibraltar Real Estate Guide.


Share this article

Related News

11/05/2025
North Gorge Gibraltar

Location and Features North Gorge is a residential development in Gibraltar's South District, one of the territory’s most desirable areas, known for its tranquility and breathtaking views across the Bay, the Strait of Gibraltar and North Africa. The development is thoughtfully designed to integrate seamlessly with its natural surroundings, ensuring re...

Read More
26/08/2025
Want to work from home? Gibraltar is your top choice

Why Gibraltar is a Top Choice for Remote WorkMore professionals across Europe are choosing Gibraltar as their remote work base. Its sunny climate, attractive tax advantages, English-speaking environment, and thriving expat community make it a top destination for those who want to balance productivity with lifestyle.For remote workers, modern Eastside apartme...

Read More
13/08/2026
Gibraltar National Day A Celebration of Unity and Identity

Gibraltar National Day 2026 – Quick FactsDate: Thursday, 10 September 2026What it celebrates: 1967 sovereignty referendumPublic holiday: YesMain events: Casemates Square, Main StreetWhat to expect: parades, music, street celebrationsWhen is Gibraltar National Day 2026?Gibraltar National Day is celebrated every year on 10 September. In 2026, National Day fall...

Read More
05/04/2025
Properties For Sale in Ocean Village Gibraltar

Architectural Wonders of Ocean Village: A Fusion of Luxury, History, and Innovation Nestled along the picturesque coastline of Gibraltar, Ocean Village stands as a testament to architectural diversity and modernity. This vibrant and dynamic waterfront neighbourhood boasts a stunning array of buildings that harmoniously blend contemporary design with the reg...

Read More